Hi,
We have a PLM system which will send SAP the eBOM. SAP will then create an mBOM from the eBOM. However the eBOM could be revised in the PLM system with an ECR/ECO process. At the same time manufacturing would like to revise the mBOM independant of the eBOM in SAP. Is this an industry best practice ? I see an issue with this approach that I could reach a stage where the eBOM is at revision level 2 and the mBOM is as revision 10 for example. How do we make sure that both are at the same revision level ? Or is it common to change the mBOM independantly of the eBOM ?
Thanks