HI,
I am getting an exception message 30 for MRP planning for a material. The issue is that there is no planned delivery time, production lead time or GR time in material master. Which other field/customization can pull back an order from 4 days to past and reschedule it?
All other orders in future are falling on the same day on which there is a requirement day in MD61. Only for the orders which are closed to system date (in future) the rescheduling is done and requirement date get pushed back.
Please help.